Functional Area: Engineering and Construction Project Type: Continuing, Capital Project Responsible Department: DEPARTMENT OF MOBILITY AND INFRASTRUCTURE Project Manager: Municipal Traffic Engineer, Mobility and Infrastructure
Capital Improvement Program
Project Description
This project is to perform a traffic calming and facility update project along Liberty Avenue through the Strip District from Grant Street to 34th Street. A three lane section will be constructed instead of the current four lane section to reduce sideswipe and head on collisions. Additional funds will be received from the federal Highway Safety Improvement Program (HSIP).
Project Justification
This is a heavily traveled corridor with very narrow travel lanes. This project has been prioritized due to safety concerns.
Shows capital project funding by source and year.
Operating Budget Impact
Once completed, these improvements will have maintenance requirements that will impact the Operating Budget.
Unexpended/Unencumbered Prior Year Funds $9,315,203